A) Project D probably has a higher IRR.
B) Project D is probably larger in scale than Project C.
C) Project C probably has a faster payback.
D) Project C probably has a higher IRR.
E) The crossover rate between the two projects is below 12%.
Correct Answer
verified
Multiple Choice
A) Lacks an objective,market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 2.42 years
B) 1.96 years
C) 2.88 years
D) 2.47 years
E) 2.85 years
Correct Answer
verified
Multiple Choice
A) Each project must have a negative NPV.
B) Since the projects are mutually exclusive,the firm should always select Project B.
C) If the crossover rate is 8%,Project B will have the higher NPV.
D) Only one project has a positive NPV.
E) If the crossover rate is 8%,Project A will have the higher NPV.
Correct Answer
verified
Multiple Choice
A) It will accept too many short-term projects and reject too many long-term projects (as judged by the NPV) .
B) It will accept too many long-term projects and reject too many short-term projects (as judged by the NPV) .
C) The firm will accept too many projects in all economic states because a 4-year payback is too low.
D) The firm will accept too few projects in all economic states because a 4-year payback is too high.
E) If the 4-year payback results in accepting just the right set of projects under average economic conditions,then this payback will result in too few long-term projects when the economy is weak.
Correct Answer
verified
Multiple Choice
A) The NPV method was once the favorite of academics and business executives,but today most authorities regard the MIRR as being the best indicator of a project's profitability.
B) If the cost of capital declines,this lowers a project's NPV.
C) The NPV method is regarded by most academics as being the best indicator of a project's profitability,hence most academics recommend that firms use only this one method and disregard other methods.
D) A project's NPV depends on the total amount of cash flows the project produces,but because the cash flows are discounted at the WACC,it does not matter if the cash flows occur early or late in the project's life.
E) The NPV and IRR methods may give different recommendations regarding which of two mutually exclusive projects should be accepted,but they always give the same recommendation regarding the acceptability of a normal,independent project.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 0$222.13
B) 0$185.11
C) 0$157.34
D) 0$174.00
E) 0$198.07
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the WACC,while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate,while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the WACC,while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider all relevant cash flows,particularly cash flows beyond the payback period.
E) The IRR method does not consider all relevant cash flows,particularly cash flows beyond the payback period.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC,then the MIRR will be less than the IRR.
D) If a project's IRR is greater than its WACC,then the MIRR will be greater than the IRR.
E) To find a project's MIRR,we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
Correct Answer
verified
Multiple Choice
A) The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
B) The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
C) The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
D) The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
E) The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project S must have a higher NPV than Project L.
B) If Project S has a positive NPV,Project L must also have a positive NPV.
C) If the WACC falls,each project's IRR will increase.
D) If the WACC increases,each project's IRR will decrease.
E) If Projects S and L have the same NPV at the current WACC,10%,then Project L,the one with the lower IRR,would have a higher NPV if the WACC used to evaluate the projects declined.
Correct Answer
verified
Multiple Choice
A) 13.84%
B) 14.53%
C) 17.29%
D) 13.28%
E) 13.70%
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B,then Project A must have the lower NPV.
B) If Project A has a higher IRR than Project B,then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
D) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
E) If a project has normal cash flows and its IRR exceeds its WACC,then the project's NPV must be positive.
Correct Answer
verified
Showing 41 - 60 of 107
Related Exams