A) depreciation
B) shipping and installation
C) increase in working capital
D) salvage value
E) decrease in sales
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The project should be accepted because its IRR (before risk adjustment) is greater than its required return.
B) The project should be rejected because its IRR (before risk adjustment) is less than its required return.
C) The accept/reject decision depends on the risk-adjustment policy of the firm.If the firm's policy were to reduce a riskier-than-average project's IRR by 1 percentage point, then the project should be accepted.
D) Riskier-than-average projects should have their IRRs increased to reflect their added riskiness.Clearly, this would make the project acceptable regardless of the amount of the adjustment.
E) Projects should be evaluated on the basis of their total risk alone.Thus, there is insufficient information in the problem to make an accept/reject decision.
Correct Answer
verified
Multiple Choice
A) Projects risks are not considered directly because the weighted average cost of capital (WACC) that is used as the required rate of return for capital budgeting decisions is based on the riskiness of the firm.As a result, all projects, no matter their risks, can be evaluated using WACC.
B) Evaluating risk is important only when the projects are similar to the firm's existing assets.
C) Most firms adjust the discount rates used to evaluate new projects that have significantly different risks than the risk associated with the firm's existing assets.
D) Firms generally increase the required rate of return used to evaluate projects that have significantly different risks than the risk associated with the firm's existing assets, regardless of whether the new projects' risks are higher or lower.
E) None of the above is a correct answer.
Correct Answer
verified
Multiple Choice
A) 2.2
B) 1.0
C) 1.8
D) 1.6
E) 2.0
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Sensitivity analysis is incomplete because it fails to consider the range of likely values of key variables as reflected in their probability distributions.
B) In comparing two projects using sensitivity analysis, the one with the steeper lines would be considered less risky, because a small error in estimating a variable, such as unit sales, would produce only a small error in the project's NPV.
C) The primary advantage of simulation is that it provides a very accurate point estimate of a project's NPV.
D) One important benefit of simulation analysis as compared to scenario analysis, is that once the analysis is complete, it provides a clear accept/reject decision rule.
E) Answers c and d are both correct.
Correct Answer
verified
Multiple Choice
A) The return on invested capital is the only relevant cash flow.
B) Only incremental cash flows are relevant to the accept/reject decision.
C) Total cash flows are relevant to capital budgeting analysis and the accept/reject decision.
D) All of the above are correct.
E) Only answers a and b are correct.
Correct Answer
verified
Multiple Choice
A) Ignoring it.
B) Adjusting the discount rate upward for increasing risk.
C) Adjusting the discount rate downward for increasing risk.
D) Picking a risk factor equal to the average discount rate.
E) Reducing the NPV by 10 percent for risky projects.
Correct Answer
verified
Multiple Choice
A) No; the expected return is less than the required return.
B) No; the IRR is less than the appropriate required rate of return.
C) Yes; the IRR is greater than the appropriate required rate of return.
D) Yes; the expected return is greater than the required return.
E) Yes; the project's risk/return combination lies above the SML.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) R6.24
B) R7.89
C) R8.87
D) R9.15
E) R10.41
Correct Answer
verified
Multiple Choice
A) Risk premium method.
B) Pure play method.
C) Accounting beta method.
D) CAPM method.
E) Answers b and c are both correct.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Be correct.
B) Be biased downward.
C) Be biased upward.
D) Possibly have a bias, but it could be upward or downward.
E) More information is needed; otherwise, we can make no reasonable statement.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) -R1,547
B) -R562
C) R0
D) R562
E) R1,034
Correct Answer
verified
Multiple Choice
A) After-tax operating cash flows will increase by R15,000.
B) After-tax operating cash flows will increase by R10,000.
C) After-tax operating cash flows will decrease by R25,000.
D) After-tax operating cash flows will decrease by R10,000.
E) Because depreciation is a non-cash expense, operating cash flows should not change.
Correct Answer
verified
Showing 1 - 20 of 103
Related Exams