A) There is a single IRR of approximately 12.7 percent.
B) This project has no IRR, because the NPV profile does not cross the X axis.
C) There are multiple IRRs of approximately 12.7 percent and 787 percent.
D) This project has two imaginary IRRs.
E) There are an infinite number of IRRs between 12.5 percent and 790 percent that can define the IRR for this project.
Correct Answer
verified
Multiple Choice
A) when decision makers are forced to compare their projections to actual outcomes, there is a tendency to improve.
B) conscious or unconscious biases are removed.
C) negative NPV projects are identified before they begin.
D) forecasts are improved.
E) all of the above are benefits of the post-audit.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 15.0%
B) 14.0%
C) 12.0%
D) 16.0%
E) 17.0%
Correct Answer
verified
Multiple Choice
A) The NPV will be positive if the IRR is less than the required rate of return.
B) If the multiple IRR problem does not exist, any independent project acceptable by the NPV method will also be acceptable by the IRR method.
C) When IRR = k (the required rate of return) , NPV = 0.
D) The IRR can be positive even if the NPV is negative.
E) The NPV method is not affected by the multiple IRR problem.
Correct Answer
verified
Multiple Choice
A) the impact of a capital budgeting decision is long term; the firm loses some decision-making flexibility when capital projects are purchased.
B) effective capital budgeting can improve the timing of asset acquisition and the quality of assets purchased.
C) the acquisition of fixed assets typically involves substantial expenditures, and before a firm spends a large amount of money, it must have the funds available.
D) capital budgeting techniques overcome the problems with error in forecasts for asset requirements and projected sales, we will still be able to determine if we should fund the project.
E) all of the above are factors that make capital budgeting important.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 6.5%
B) 11.5%
C) 16.5%
D) 20.0%
E) The NPV profiles of these two projects do not cross.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Equal to the internal rate of return.
B) Too high.
C) Greater than the internal rate of return.
D) Too low.
E) Less than the internal rate of return.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the required rate of return while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the required rate of return while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider the inflation premium.
E) The IRR method does not consider all relevant cash flows, and particularly cash flows beyond the payback period.
Correct Answer
verified
Multiple Choice
A) it is the simplest and oldest formal model to evaluate capital budgeting model.
B) it directly accounts for the time value of money.
C) it ignores cash flows beyond the payback period.
D) it always leads to decisions that maximise the value of the firm.
E) it incorporates risk into the discount rate used to solve the payback period.
Correct Answer
verified
Multiple Choice
A) The project with the higher NPV may not always be the project with the higher IRR.
B) The project with the higher NPV may not always be the project with the higher MIRR.
C) The project with the higher IRR may not always be the project with the higher MIRR.
D) All of the above answers are correct.
E) Answers a and c are both correct.
Correct Answer
verified
Multiple Choice
A) All else equal, a project's IRR increases as the required rate of return declines.
B) All else equal, a project's NPV increases as the required rate of return declines.
C) All else equal, a project's IRR is unaffected by changes in the required rate of return.
D) Answers a and b are both correct.
E) Answers b and c are both correct.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The lump sum payment, since it has the larger future value.
B) Monthly payments, since you do not have to wait so long to receive your money.
C) Either one, since they have the same present value.
D) The lump sum payment, since it has the larger present value.
E) Monthly payments, since it has the larger present value.
Correct Answer
verified
Showing 61 - 80 of 94
Related Exams