Correct Answer
verified
Multiple Choice
A) It will accept too many long-term projects and reject too many short-term projects (as judged by the NPV) .
B) The firm will accept too many projects in all economic states because a 4-year payback is too low.
C) The firm will accept too few projects in all economic states because a 4-year payback is too high.
D) If the 4-year payback results in accepting just the right set of projects under average economic conditions, then this payback will result in too few long-term projects when the economy is weak.
E) It will accept too many short-term projects and reject too many long-term projects (as judged by the NPV) .
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The crossover rate must be greater than 10%.
B) If the WACC is 8%, Project X will have the higher NPV.
C) If the WACC is 18%, Project Y will have the higher NPV.
D) Project X is larger in the sense that it has the higher initial cost.
E) The crossover rate must be less than 10%.
Correct Answer
verified
Multiple Choice
A) $24.14
B) $26.82
C) $29.80
D) $33.11
E) $36.42
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The discounted payback method eliminates all of the problems associated with the payback method.
B) When evaluating independent projects, the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
C) To find the MIRR, we discount the TV at the IRR.
D) A project's NPV profile must intersect the X-axis at the project's WACC.
E) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the NPV method provides.
Correct Answer
verified
Multiple Choice
A) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
B) A project's MIRR can never exceed its IRR.
C) If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV.
D) If the NPV is negative, the IRR must also be negative.
E) If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $5.47
B) $6.02
C) $6.62
D) $7.29
E) $7.82
Correct Answer
verified
Multiple Choice
A) Since the smaller project has the higher IRR, the two projects' NPV profiles will cross, and the larger project will look better based on the NPV at all positive values of WACC.
B) If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger, longer-term projects, regardless of how high or low the WACC is.
C) Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects' NPV profiles will cross, and the larger project will have the higher NPV if the WACC is less than the crossover rate.
D) Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects' NPV profiles will cross, and the smaller project will look better if the WACC is less than the crossover rate.
E) Since the smaller project has the higher IRR, the two projects' NPV profiles cannot cross, and the smaller project's NPV will be higher at all positive values of WACC.
Correct Answer
verified
Multiple Choice
A) 9.32%
B) 10.35%
C) 11.50%
D) 12.78%
E) 14.20%
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
B) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
C) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
D) If a project has normal cash flows and its IRR exceeds its WACC, then the project's NPV must be positive.
E) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
Correct Answer
verified
Multiple Choice
A) 1.88 years
B) 2.09 years
C) 2.29 years
D) 2.52 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) More of Project B's cash flows occur in the later years.
B) We must have information on the cost of capital in order to determine which project has the larger early cash flows.
C) The NPV profile graph is inconsistent with the statement made in the problem.
D) The crossover rate, i.e., the rate at which Projects A and B have the same NPV, is greater than either project's IRR.
E) More of Project A's cash flows occur in the later years.
Correct Answer
verified
Multiple Choice
A) -$18.89
B) -$19.88
C) -$20.93
D) -$22.03
E) -$23.13
Correct Answer
verified
Showing 81 - 100 of 108
Related Exams