A) The project will also be acceptable using payback criteria.
B) The IRR should be calculated to insure that the project's projected rate of return exceeds the required rate of return.
C) The project should be accepted without any further consideration,assuming we are confident that the cash flows and the required rate of return have been properly estimated.
D) Only answers a and c are correct.
E) None of the above is correct.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Ignoring it.
B) Adjusting the discount rate upward for increasing risk.
C) Adjusting the discount rate downward for increasing risk.
D) Picking a risk factor equal to the average discount rate.
E) Reducing the NPV by 10 percent for risky projects.
Correct Answer
verified
Multiple Choice
A) sunk cost
B) opportunity cost
C) externality
D) incremental cash flow
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 2 years
B) 4 years
C) 6 years
D) 8 years
E) 10 years
Correct Answer
verified
Multiple Choice
A) 8%
B) 10%
C) 12%
D) 14%
E) 16%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Repatriation
B) Expropriation
C) Exchange Rate
D) Political
Correct Answer
verified
Multiple Choice
A) Internal rate of return.
B) Net present value.
C) Payback.
D) Discounted payback.
E) Answers c and d are both correct.
Correct Answer
verified
Multiple Choice
A) Changes when the required rate of return changes.
B) Is equal to the annual net cash flows divided by one half of the project's cost when the cash flows are an annuity.
C) Must exceed the required rate of return in order for the firm to accept the investment.
D) Is similar to the yield to maturity on a bond.
E) Answers c and d are both correct.
Correct Answer
verified
Multiple Choice
A) Increase the IRR of the asset to reflect the greater risk.
B) Increase the NPV of the asset to reflect the greater risk.
C) Reject the asset,since its acceptance would increase the risk of the firm.
D) Ignore the risk differential if the asset to be accepted would comprise only a small fraction of the total assets of the firm.
E) Increase the required rate of return used to evaluate the project to reflect the higher risk of the project.
Correct Answer
verified
Multiple Choice
A) Project B because of higher NPV.
B) Project B because of higher IRR.
C) Project A because of higher NPV.
D) Project A because of higher IRR.
E) Neither,because both have IRRs less than the required return.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) opportunity cost
B) sunk cost
C) incremental cash flow
D) externality
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Well-diversified stockholders,because it may affect debt capacity and operating income.
B) Management,because it affects job stability.
C) Creditors,because it affects the firm's credit worthiness.
D) All of the above are correct.
E) Only answers a and c are correct.
Correct Answer
verified
Multiple Choice
A) Sensitivity analysis.
B) Beta,or CAPM,analysis.
C) Monte Carlo simulation.
D) Scenario analysis.
E) All of the above are discussed in the text as methods of analyzing risk in capital budgeting.
Correct Answer
verified
Showing 41 - 60 of 192
Related Exams