Filters
Question type

Study Flashcards

_____ includes both the identification of potential risk and the evaluation of the potential impact of the risk.

Correct Answer

verifed

verified

The purchase of insurance on certain items is a risk sharing method.

A) True
B) False

Correct Answer

verifed

verified

On global projects with a large amount of political risk, the highest portion of risk may be _____.


A) in the execution phase
B) in the planning stage
C) toward the end of the project
D) in the early phases of the project
E) during the procurement of goods and services

F) B) and E)
G) All of the above

Correct Answer

verifed

verified

On highly complex projects, _____.


A) basic measures such as percentage of activities completed and percentage of budget spent are adequate for budget evaluation
B) the process for evaluating risk is more informal with risk assessment meetings conducted every once in a while to assess risks at different phases of the project
C) an outside expert may be included in the risk assessment process and the risk assessment plan may take a more prominent role in the project execution plan
D) the project management team may develop a list of items perceived to be higher risk and track them during project reviews
E) the project manager may informally track items that may be considered risk items

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

Risks that can be anticipated, such as exceptionally bad weather, are called _____.


A) risk events
B) uncertain risks
C) known risks
D) random risks
E) risk aversions

F) D) and E)
G) B) and D)

Correct Answer

verifed

verified

Describe the Monte Carlo simulation.

Correct Answer

verifed

verified

The Monte Carlo simulation simulates a p...

View Answer

Risk sharing involves partnering with others to share responsibility for the risk activities.

A) True
B) False

Correct Answer

verifed

verified

On projects with a low complexity profile, _____.


A) the process for evaluating risk is more formal with risk assessment meetings held during the life of the project to assess risks at different phases of the project
B) an outside expert may be included in the risk assessment process and the risk assessment plan may take a more prominent role in the project execution plan
C) the project management team may develop a list of items perceived to be higher risk and track them during project reviews
D) the project manager may informally track items that may be considered risk items
E) statistical models are sometimes used to evaluate risk because there are too many different possible combinations of risks to calculate them one at a time

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is true about project risk?


A) Risk seems to have a negative correlation to complexity.
B) High-risk projects are in very few cases highly complex.
C) The risk breakdown analysis explores the project from the perspective of what elements on the project add to project complexity.
D) The project team develops a risk breakdown structure that addresses the items that are identified as high risk.
E) The process of conducting a risk analysis focuses on developing an understanding of what can go wrong and the likelihood that it will go wrong.

F) B) and C)
G) C) and E)

Correct Answer

verifed

verified

The possible loss that is associated with the business purpose of the project is called _____.


A) project risk
B) organizational risk
C) strategic risk
D) external risk
E) financial risk

F) All of the above
G) A) and E)

Correct Answer

verifed

verified

Which of the following is true about contingency funds?


A) Contingency funds are funds set aside by the client to address unforeseen events that cause the project costs to increase.
B) Projects with a high risk profile will typically have a small contingency budget.
C) Contingency is typically managed as multiple line items in the project budget.
D) Allocating the contingency budget to the items in the budget that have low risk allows the project team to track the use of contingency against the risk plan.
E) The availability of contingency funds in the line item budget may increase the use of contingency funds to solve problems rather than finding alternative solutions.

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

The _____ is the plan to reduce or eliminate loss from unexpected events.


A) risk transfer plan
B) risk avoidance plan
C) risk acceptance plan
D) risk deflection plan
E) risk mitigation plan

F) B) and E)
G) B) and C)

Correct Answer

verifed

verified

A project with new and emerging technology will have a low complexity rating and a correspondingly low risk.

A) True
B) False

Correct Answer

verifed

verified

High scores for environmental complexity imply high risks for delay and _____.


A) unknown factors
B) limited resources
C) expensive resolution to lawsuits
D) organizational complexity
E) lack of clarity in project and scope statements

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

As the project progresses into the execution phase, _____.


A) risks need to be checked off on activities that have been performed
B) the total risk on the project typically increases
C) risks are identified with each major group of activities
D) a risk response plan can be used to identify increasing levels of detailed risk analysis
E) the risk breakdown structure needs to be examined to be sure all the risk events have been avoided

F) B) and C)
G) None of the above

Correct Answer

verifed

verified

According to Tzvi Raz, Aaron Shenhar, and Dov Dvir's risk management studies, which of the following is true about risk management practices?


A) Risk management is widely used.
B) The projects that were most likely to have a risk management plan were those that were actually high risk.
C) When risk management practices were applied to projects, they appeared to be moderately related to the success of the project.
D) The risk management approach influenced the meeting of project schedules and cost goals but exerted more influence on project product quality.
E) Good risk management increases the likelihood of a successful project.

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

After potential risks have been identified, the project team then evaluates the risk based on the probability that the risk event will occur and the potential loss associated with the event.

A) True
B) False

Correct Answer

verifed

verified

Proactive project managers:


A) do not consider risks.
B) prefer to be optimistic.
C) will develop elaborate risk management programs for their projects.
D) are more confident in their ability to handle unexpected events without prior planning.
E) avoid taking risks whenever possible.

F) A) and C)
G) C) and D)

Correct Answer

verifed

verified

What are the elements of risk management during the initiation phase of the project?

Correct Answer

verifed

verified

Risk is associated with things that are ...

View Answer

Risk seems to have an) _____ correlation to complexity.

Correct Answer

verifed

verified

Showing 21 - 40 of 65

Related Exams

Show Answer