A) 2,477
B) 1,680
C) 2,211
D) 2,101
E) 2,742
Correct Answer
verified
Multiple Choice
A) The proposed new project would have more stand-alone risk than the firm's typical project.
B) The proposed new project would increase the firm's corporate risk.
C) The proposed new project would increase the firm's market risk.
D) The proposed new project would not affect the firm's risk at all.
E) The proposed new project would have less stand-alone risk than the firm's typical project.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 0$66,796
B) 0$75,339
C) 0$92,426
D) 0$77,669
E) 0$61,359
Correct Answer
verified
Multiple Choice
A) $27,229
B) $24,573
C) $22,138
D) $21,473
E) $26,122
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project A,which has average risk and an IRR = 9%.
B) Project B,which has below-average risk and an IRR = 8.5%.
C) Project C,which has above-average risk and an IRR = 11%.
D) Without information about the projects' NPVs we cannot determine which one or ones should be accepted.
E) All of these projects should be accepted as they will produce a positive NPV.
Correct Answer
verified
Multiple Choice
A) Changes in net operating working capital.
B) Shipping and installation costs for machinery acquired.
C) Cannibalization effects.
D) Opportunity costs.
E) Sunk costs that have been expensed for tax purposes.
Correct Answer
verified
Multiple Choice
A) $5,500
B) $4,345
C) $5,995
D) $5,885
E) $6,710
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 55,915
B) 061,507
C) 054,238
D) 048,087
E) 043,614
Correct Answer
verified
Multiple Choice
A) In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt,failure to include interest expense as a cost when determining the project's cash flows will lead to an upward bias in the NPV.
B) In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt,failure to include interest expense as a cost when determining the project's cash flows will lead to a downward bias in the NPV.
C) The existence of any type of "externality" will reduce the calculated NPV versus the NPV that would exist without the externality.
D) If one of the assets to be used by a potential project is already owned by the firm,and if that asset could be sold or leased to another firm if the new project were not undertaken,then the net proceeds that could be obtained should be charged as a cost to the project under consideration.
E) If one of the assets to be used by a potential project is already owned by the firm but is not being used,then any costs associated with that asset is a sunk cost and should be ignored.
Correct Answer
verified
Multiple Choice
A) $10,329
B) $10,681
C) $13,029
D) $11,738
E) $11,151
Correct Answer
verified
Multiple Choice
A) Sensitivity analysis is a good way to measure market risk because it explicitly takes into account diversification effects.
B) One advantage of sensitivity analysis relative to scenario analysis is that it explicitly takes into account the probability of specific effects occurring,whereas scenario analysis cannot account for probabilities.
C) Well-diversified stockholders do not need to consider market risk when determining required rates of return.
D) Market risk is important,but it does not have a direct effect on stock prices because it only affects beta.
E) Simulation analysis is a computerized version of scenario analysis where input variables are selected randomly on the basis of their probability distributions.
Correct Answer
verified
Multiple Choice
A) -$35,149
B) -$34,446
C) -$28,119
D) -$33,040
E) -$41,827
Correct Answer
verified
Multiple Choice
A) The firm's corporate,or overall,WACC is used to discount all project cash flows to find the projects' NPVs.Then,depending on how risky different projects are judged to be,the calculated NPVs are scaled up or down to adjust for differential risk.
B) Differential project risk cannot be accounted for by using "risk-adjusted discount rates" because it is highly subjective and difficult to justify.It is better to not risk adjust at all.
C) Other things held constant,if returns on a project are thought to be positively correlated with the returns on other firms in the economy,then the project's NPV will be found using a lower discount rate than would be appropriate if the project's returns were negatively correlated.
D) Monte Carlo simulation uses a computer to generate random sets of inputs,those inputs are then used to determine a trial NPV,and a number of trial NPVs are averaged to find the project's expected NPV.Sensitivity and scenario analyses,on the other hand,require much more information regarding the input variables,including probability distributions and correlations among those variables.This makes it easier to implement a simulation analysis than a scenario or sensitivity analysis,hence simulation is the most frequently used procedure.
E) DCF techniques were originally developed to value passive investments (stocks and bonds) .However,capital budgeting projects are not passive investments - managers can often take positive actions after the investment has been made that alter the cash flow stream.Opportunities for such actions are called real options.Real options are valuable,but this value is not captured by conventional NPV analysis.Therefore,a project's real options must be considered separately.
Correct Answer
verified
Multiple Choice
A) Using some of the firm's high-quality factory floor space that is currently unused to produce the proposed new product.This space could be used for other products if it is not used for the project under consideration.
B) Revenues from an existing product would be lost as a result of customers switching to the new product.
C) Shipping and installation costs associated with a machine that would be used to produce the new product.
D) The cost of a study relating to the market for the new product that was completed last year.The results of this research were positive,and they led to the tentative decision to go ahead with the new product.The cost of the research was incurred and expensed for tax purposes last year.
E) It is learned that land the company owns and would use for the new project,if it is accepted,could be sold to another firm.
Correct Answer
verified
Showing 21 - 40 of 75
Related Exams